Horizontal Stabilizer

Empennage Horizontal Stabilizer 

Finished Horizontal Stabilizer

February 9, 2021April 1, 2021 Jesse 0 Comments

I received the Torque Seal to finish off the rear spar. I opted for orange (many colors available). This stuff

Read more
Horizontal Stabilizer 

HS Spar Assembly

January 16, 2021January 16, 2021 Jesse 0 Comments

It’s assembly time! I began with the rear spar. I found that all of these rivets could be squeezed using

Read more
Horizontal Stabilizer Priming 

Priming Horizontal Stabilizer

January 2, 2021January 11, 2021 Jesse 0 Comments

1/1/2021 – Since it’s winter and I have a heated garage without a paint booth setup, I’m running the parts

Read more
Horizontal Stabilizer 

HS Deburring and Dimpling

December 28, 2020December 28, 2020 Jesse 0 Comments

I spent quite a few hours deburring all edges, holes and dimpling. For the long, straight edges I used a

Read more
Horizontal Stabilizer 

Right Side Horizontal Stabilizer

November 29, 2020November 29, 2020 Jesse 0 Comments

With the left side done, I proceeded to complete the right side. This went a good bit faster now that

Read more
Horizontal Stabilizer 

Progress Continues On HS

November 19, 2020November 19, 2020 Jesse 0 Comments

I got the build back up to speed with where I had left off, which was clecoing the HS skeleton

Read more
Empennage Horizontal Stabilizer 

HS: More Front Spar Work

June 11, 2020June 11, 2020 Jesse 0 Comments

6/1/20 – Bent the HS-702 tabs to 6 degrees per plans. Clamped HS-00001 spar doublers to the HS-702’s as well

Read more
Empennage Horizontal Stabilizer 

HS Rear And Front Spar Assembly

June 3, 2020June 11, 2020 Jesse 0 Comments

5/30/20 – After waiting for about a week for additional Clecos, they arrived. I also receive a Scotch-Brite 6″ 7S

Read more
Empennage Horizontal Stabilizer 

Beginning Horizontal Stabilizer, Days 1-3

May 26, 2020June 11, 2020 Jesse 0 Comments

With my shop all setup, most of the needed tools acquired and parts ready to go, it was time to

Read more

Recent Posts

  • Building Vertical Stabilizer
  • Finished Horizontal Stabilizer
  • HS Spar Assembly
  • Priming Horizontal Stabilizer
  • Primers: A Salt Fog Test

Recent Comments

  • Jesse on Primers: A Salt Fog Test
  • Drew Harthorn on Primers: A Salt Fog Test

Archives

  • April 2021
  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • August 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020

Categories

  • Build Preparation (16)
    • Education (2)
    • Practice Kits (3)
    • The Workshop (10)
  • Empennage (11)
    • Horizontal Stabilizer (9)
  • Priming (2)
Copyright © 2023 Jesse's RV-7A Build. All rights reserved.
Theme: ColorMag by ThemeGrill. Powered by WordPress.